Location: Hartville, OH
Our Contract: $2,027,500.00
GC: Hammond Construction Inc.
Description: This 171,354-sf construction combined both the middle school and high school transforming the once 9-12 high school into a 7-12 college-like campus. Multiple interior renovations, selective demolition and 2 additions were included in the 8 phases of construction. The first addition consisted of a two-story, 110,000-sf front building. This project was complete while the school was occupied the whole time.